Earned-Value Analysis. A Project Budget Calls For The Following Expenditures:

 

Define each term in your own words, calculate these values for the above project, and show your work:

  1. Budgeted cost baseline (make a graph illustrating this one)
  2. Budget at completion (BAC)
  3. Planned value (PV) as of May 1
  4. Earned value (EV) as of May 1 if the foundation work is only two-thirds complete. Everything else is on schedule.
  5. SV as of May 1.
  6. Actual cost as of May 1 is $160,000. Calculate the cost variance (CV) as of May 1.
  7. Schedule performance index (SPI)
  8. Cost performance index (CPI)
  9. Estimate to complete (ETC), assuming that the previous cost variances will not affect future costs
  10. Estimate at completion (EAC)

Write my Essay. I am looking for someone to write my essay? Welcome, you are at the right place. Our writes will help you out. Provide us with the instructions and one of our writers will deliver a unique, no plagiarism, and professional paper.

Get help with your toughest assignments and get them solved by our team of expert writers. Get your Essay from A Simple Idea to a complete paper. Save time, money and get quality papers.

Get Professional Assistance with Writing Your Papers!

Hire an expert to write my paper for me

Get this essay done before the deadline! Tell us about your assignment and we will find the best writer for your project

Get Help Now!
PLACE YOUR ORDER